c) Constant rate of strain testing
Golder conducted two constant rate of strain (CRS) tests on FRV Unit A specimens as part of the advanced laboratory testing programme. This testing was undertaken using a GDS Constant Rate of Strain (GDSCRS) system, in which an advanced velocity-controlled load frame is used to apply vertical stress to a laterally-confined, back-pressured test specimen. Back pressure is supplied via a GDS pressure/volume controller.
Figure 13: The GDS Constant Rate of Strain system (GDSCRS).
The two CRS tests performed on FRV Unit A specimens enabled the ITRB to estimate values of typical consolidation parameters (e.g., coefficient of consolidation, pre-consolidation pressure), while also highlighting a reduction in the constrained modulus (i.e., one-dimensional stiffness) as the vertical effective stress increased beyond approximately 1000 – 1500 kPa. It was proposed that this reduction in stiffness at higher vertical stress levels was caused by soil particle crushing or disaggregation.
INSIGHTS FROM THE ADVANCED LABORATORY TESTING PROGRAMME The advanced laboratory testing programme provided a number of important insights into the loading response of the tailings and FRV Unit A foundation materials, assisting the ITRB in understanding the mechanism by which the Cadia NTSF embankment slumped on the 9th of March 2018. These insights included:
- Monotonic direct simple shear (DSS) testing of FRV Unit A specimens within a GDS EMDCSS highlighted the strain-weakening response of this previously unidentified embankment foundation material. This ultimately led the ITRB to conclude that the peak strength of this material had begun to be exceeded during embankment construction, particularly following excavation of material at the embankment toe and construction of the Stage 1 buttress, resulting in progressive deformation within the foundation. The deformation rapidly accelerated prior to the slump occurring.
- ‘Constant shear drained’ (CSD) triaxial testing of reconstituted tailings specimens within a GDS TAS suggested that some locations within the tailings had approached an unstable stress state during embankment construction, and that rapid collapse could potentially being triggered (i.e., liquefaction could occur) should a small amount of rapid loading be applied. The accelerating deformation within the embankment foundation provided the trigger to cause the tailings to liquefy, which in turn significantly increased the load on the embankment and the already weakened foundation. This additional load could not be resisted, and the embankment slump occurred.
- Cyclic DSS testing of tailings specimens within a GDS EMDCSS demonstrated that two low-magnitude earthquakes experienced at the Cadia worksite on the 8th of March 2018 did not induce significant excess pore water pressures and shear strains within the tailings. This finding was important, as it established that the low-magnitude earthquakes did not contribute to the embankment slump.
| SUMMARY
A mobile slump that occurred in a section of embankment at the Cadia Valley Operations (Cadia) Northern Tailings Storage Facility on the 9th of March 2018 was determined to have been caused by progressive deformation of a previously unidentified low-density foundation layer during ongoing embankment construction, which ultimately triggered liquefaction of impounded tailings. Once liquefied, the tailings significantly increased the load applied to the embankment, which the already-weakened foundation was unable to resist. This resulted in the embankment slumping, however timely evacuation of the worksite by Cadia personnel meant the slump created no obvious social or environmental impacts.
The technical cause of the embankment slump described above was concluded through investigation by an Independent Technical Review Board (ITRB). A laboratory testing programme was commissioned as part of the ITRB investigation, with a number of advanced test apparatuses produced by GDS Instruments (GDS) being utilised by Golder’s Perth laboratory (Golder) to produce monotonic and cyclic direct simple shear (DSS), triaxial, bender element, and constant rate of strain test data. Such testing provided the ITRB with important insights into the response of the tailings and foundation materials to load, assisting the ITRB in determining the technical mechanism of the slump. The testing also helped the ITRB to rule out two lowmagnitude earthquakes as the cause of the tailings liquefying. This case study therefore demonstrates the value advanced laboratory testing programmes can provide when assessing how foundation soils and impounded materials may perform under loadings applied by embankment construction, and/or seismic activity, at tailings storage facilities.
REFERENCES
Jefferies, M.; Morgenstern, N. R.; Van Zyl, D.; Wates, J. (2019). Report on NTSF Embankment Failure Cadia Valley Operations for Ashurst Australia By Independent Technical Review Board. 17 April 2019. Newcrest Mining Limited. https://www.newcrest. com/sites/default/files/2019-10/190417_Report%20on%20 NTSF%20Embankment%20Failure%20at%20Cadia%20for%20 Ashurst.pdf.
Newcrest Mining Limited. (2019). Cadia NTSF Embankment Slump. Available at: https://www.youtube.com/ watch?v=DyyxLmPdVaE.
|